§ 6-87. Preliminary construction requirement.  


Latest version.
  • Prior to beginning construction, the following must be complied with:

    (1)

    Side and rear property lines shall be staked and marked with either wire or nylon cord running the entire distance.

    (2)

    The City Building Official shall be notified when batter boards are erected and shall verify the setbacks before construction can proceed.

    (3)

    Where street curbs exist, the holder of the permit shall be responsible to repair any damage before the certificate of occupancy is issued.

    (4)

    A temporary construction driveway, unless a permanent surface exists, shall be established consisting of not less than four inches of flex base material extending ten feet into the property.

    (5)

    Cut trees, brush and other debris shall be removed within 30 days and shall not be permitted to accumulate during the construction period so as to become unsightly, present a fire hazard or become a nuisance.

    (6)

    New construction shall require a dumpster on site to prevent the accumulation of trash and debris. The City Building Official may require a dumpster on any other project where a permit is to be issued. Dumpsters shall be obtained only from those businesses having a franchise or other contractual agreement with the City to provide solid waste disposal services.

(Ord. No. 100-03-07, art. II, § 9, 7-17-2007)